  Newton County Wastewater
   
   
Bid Date: 9/8/2009; 12:00 p.m. Central Time
Atlas Estimator: Stu Huckelberry
 Atlas Project Manager: Steve Rich
 Atlas Project Administrator: Elizabeth Golden
Specifications: Click here for specifications
Drawings: Click here for drawings
Bid Schedule: See specifications for bid schedule
Addenda:  Click here for Addendum 1
 
Addendum 2 only extended the bid date

Click here for Addendum 3

Click here for Addendum 4

Click here for Addendum 5

   
   
   
Project Location: Intersection of County Roads 300 East & 500 South
Bid Hold Period: 60 days
Project Duration: 160 days
Liquidated Damages: $500
Tax Exempt: Yes